The WorkFace Planning Model 1) Develop the FIWP Templates Templates can be based on discipline (civil, scaffolding, structural, piping, electrical, etc.) and / or what is being constructed (pipe rack, coker, fractionation tower, etc.) The use of templates will improve consistency, completeness and accuracy of the project FIWP.
2) Prepare the Project FIWP Using the templates as a starting point, build all the required FIWP. The resource requirements, special instructions, special conditions and risk plans need to be adapted to reflect the details for the FIWP in question.
3) Confirm Ready for Release Responsible parties, which always include foremen, review the FIWP to ensure the completeness and accuracy of the following:
4) Release the Project FIWP An FIWP can only be released:
Note: Resources can be shared by more than one FIWP (e.g., crane)
Foremen will execute the Project FIWP as prepared,
with discretionary modifications or with approved changes.
Project Control will monitor performance. Quality Assurance will audit the FIWP process. Based on these performance and audit results, planners may modify, revise or adjust the project FIWP and / or the FIWP templates as necessary.
|
||||||||||||||||||