Q1)
Won’t large oil and gas construction projects take years to
plan based on 2 week maintenance projects being planned up to two
years in advance? A1)
No, the work face planning model develops FIWP differently
than the maintenance model.
^ Back to top ^
Q2) Aren’t
maintenance projects routine, even predictable, while large construction
projects are unique? A2)
Conditions that will be encountered in a maintenance project
can not be known until vessels are opened and the physical condition
is examined. Large oil and gas construction projects are unique,
but elements in them are repetitive. The uniqueness of large oil
and gas construction projects requires planning even more than
maintenance projects.
^ Back to top ^
Q3) Do we really
need to plan to this level of detail, can’t skilled foremen
execute from the CWP? A3)
While this may work on small projects the complexity, large number
of interdependencies and conflicting and excessive demands on
foreman’s time require dedicated planners developing detailed
work plans.
^ Back to top ^
Q4)
Won’t extra planning increase overhead
and would result in higher total costs?
A4) Potential increases
in labor productivity of 25% to 30% would more than cover increased
overhead costs. Owners are willing to invest in higher overhead
costs to achieve lower total costs.
Cost-Benefit Analysis:
Assuming labour is 40% of Total Installed
Cost (TIC):
2% increase in labour costs for workface
planners and support staff = 0.8% of TIC
25% reduction in labour costs due to
improved labour efficiency and effectiveness = 10% of TIC
Therefore, for each $100 million of construction,
WFP could save ~ $9 million.
^ Back to top ^
Q5) Won’t
foremen resent having someone else plan their projects?
A5) Prior
to the current trend of fast tracking projects, dedicated planners
developed detailed work plans that allowed foremen to focus on running
the crews. Foremen will accept well-designed plans developed by
others, provided the foremen themselves have input.
^ Back to top ^
Q6) Isn’t
it necessary for all engineering to be completed prior to developing
FIWP?
A6) FIWP
can be developed for those parts of the project where engineering
is complete. Planners need to be established early in the project
during the engineering phase.
^ Back to top ^
Q7)
If using WFP in large oil and gas construction
projects worked, wouldn’t someone be using it? A7)
The following companies are using WorkFace Planning on their projects:
CNRL, Nexen, Opti, PetroCanada, Shell,
Suncor, Syncrude, Total.
^ Back to top ^
Q8)
How many planners will be required and where will they
come from?
A8) To implement WorkFace Planning
on large projects between 1% and 2% of the labour force will be
workface planners. As this is a new position, planners will need
to be selected and trained. These dedicated planners will need
to be developed from people who have been senior foremen, general
foremen or construction superintendents.
^ Back to top ^
Q9)
How are we going to find the time to complete
the FIWP which are going to require a lot of work?
A9) The extra cost
and time to complete the FIWP will be small in comparison to the
possible prize – the ROI on the project. The payoff can
be large in comparison to the extra cost.
^ Back to top ^
Q10)
How big is an FIWP?
A10) Typically
construction is organized on two week look ahead schedules. Therefore
an FIWP will normally cover a one to two week work period for
a foreman’s crew. However, the size of an FIWP depends on
the complexity of the work. There may be situations where smaller
FIWP could be required (e.g., commissioning, start-up, etc.)
^ Back to top ^
Q11) Why can I not go from an EWP to an FIWP?
A11) Because the EWP, CWP and FIWP are different things, an EWP is an engineering deliverable, a CWP is a construction deliverable. An EWP is a CWP deliverable, it is part of a CWP. A FIWP is a construction deliverable broken down from a higher level construction deliverable, the CWP. The EWP does not account for scaffolding, construction equipment, subcontractors, manhours, etc.
^ Back to top ^
Q12)
Who develops the CWP?
A12) The CWP is developed by either the construction contingent of an EPC or the construction contractor who will perform the work. In the absence of the construction contractor the owner construction management team will develop the CWPs.
^ Back to top ^
Q13)
How many EWPs in a CWP?
A13) This is dependant on the scope of work but typically there will exist a 1:1 relationship or N:1 where N is the EWP.
^ Back to top ^
Q14) What is in a CWP?
A14) Refer to the CWP template in Appendix B of the CWP Best Practices Report.
^ Back to top ^ |